What should I tell a customer before gutter work starts?

Service Penguin 8 min read Reviewed
Clean seamless gutters on suburban home after gutter work

The short answer

Before gutter work starts, tell the customer the exact scope in writing: gutter material, size, color, downspout count and where each downspout drains. List what the price excludes, such as fascia repair, painting and underground drains. Say whether a permit is needed and who pulls it. Give a prep list, an arrival window, the weather policy, and how the finished gutters will be water-tested.

Key points

  1. Before gutter work starts, give the customer the full scope in writing, including material, size, downspout locations and what the price excludes.
  2. Permit rules for gutter work vary by city and state, so confirm with the local building department and tell the customer who pulls any permit and whether the cost is included.
  3. A prep list asking the customer to move cars, grills and patio furniture and to keep kids and pets away makes install day safer and smoother.
  4. Dated before photos and written messages are the simplest proof of what a gutter customer was told.
  5. Check-in rate equals check-in calls and texts divided by jobs, times 100, and a falling rate shows the pre-job message is doing its job.

Before gutter work starts, tell the customer five things in writing: exactly what you're installing, what's not included, whether a permit is needed and who pulls it, what to move away from the house, and when the crew will arrive. Add how you'll test the finished gutters and what happens if the weather turns. A customer who knows all of that is far less likely to call to ask, or to argue later.

Most trouble between a gutter pro and a homeowner is silence. The homeowner doesn't know the old gutters may hide soft fascia, doesn't know where the downspout will empty, and doesn't know the crew shows up at 8. One short message a few days out covers most of it.

Which details should I tell a customer before gutter work starts in writing?

Put the full scope in writing before the crew rolls: material, gauge if you specified one, color, width, profile, downspout count and size, and where each downspout will drain. "New gutters" leaves room for the customer to picture something different from what shows up.

Explain why the size is what it is. Gutters should match the water coming off the roof, not just the size of the old ones; New York's 2025 plumbing code, for example, sizes horizontal gutters by roof-surface flow rate. The same code calls for watertight joints and gutter and downspout materials compatible with the roof surface.

Then list what the price leaves out. A gutter estimate commonly excludes:

  • Fascia or soffit repair
  • Rotten roof edges
  • Siding damage and chimney flashing
  • Underground drains and grading
  • Painting
  • Hauling away old gutters, if you don't include it
  • Repairs caused by hidden damage found once the old gutters come off

Say plainly that new gutters don't fix grading, foundation drainage or a crushed underground pipe. If extensions, splash blocks or a buried drain are part of the job, name them. If not, say so.

Tell them how you'll finish: a slope check, then a water test. The New York code linked above specifies pouring at least 1 gallon of water into the end of the gutter. Customers like knowing the test happens, and it gives you a result to show them.

Do I need to tell the customer about a permit?

A gutter pro should tell the customer whether a permit is required, who will get it, and whether its cost is in the price. Requirements vary by city and state. Some places exempt limited gutter replacement while others want a permit for repair or alteration work, and the New Orleans guide to building permits is one example of a city spelling out what needs one.

Check with the local building department for each job instead of promising that no permit is needed. Where a permit applies, New York's code requires it to be issued before covered work begins. Rules change, so confirm with the city or state, and talk to an attorney if a contract question comes up.

What should the customer do to get the house ready?

Ask the customer to clear a working strip along every wall you'll touch, by the night before. That means cars out of the driveway near the house, and patio furniture, grills, kids' toys and planters moved away from the walls. If anything stays, photograph it before you start.

Ask them to keep children and pets away from ladders, falling debris and the work area until cleanup is done. Old sections, screws and hangers come down from height during a tear-off.

Tell them how ladders will be set: on firm, level ground, not on landscaping, decks or wet surfaces. An Occupational Health & Safety summary of OSHA gutter standards notes extension ladders go at about a 75-degree angle and extend 3 feet above the landing when used for access, and that residential construction work 6 feet or more up generally requires fall protection. Mention that the crew uses a stand-off so no ladder weight rests on the new gutter.

How wide should my arrival window be for a gutter crew?

Make the arrival window as narrow as you can reliably hit, and no narrower. The first install of the day can usually get a tight window, like 8:00 to 8:30, because nothing ahead of it can run long. A second job behind a full tear-off needs a wider one, since hidden fascia rot or a stubborn old hanger can add an hour.

Clean home entrance with potted plants and closed door

Send the window when you book, then confirm it the morning of. Say up front that lightning, high wind, ice or heavy rain may push the job for safety and quality, so a reschedule call doesn't feel like a broken promise.

What should I tell a customer when I am running late?

Tell the customer before the window closes, give a new time you can hit, and keep the reason to one line. "Running about 45 minutes behind, new arrival 10:15" beats a perfect excuse sent at 10:30. One honest update heads off the "are you still coming?" call and the feeling of being ignored.

What should I send a customer after the job?

Send a short summary the same day: what you installed, that the water test passed, where each downspout drains, and anything you found that still needs attention, with photos. If the old gutters hid soft fascia you didn't repair, the summary is where that goes on record.

How do I prove what I told a customer?

Proof comes from dated photos and written messages, not memory. Before the first ladder goes up, photograph the existing gutters, fascia, roof edges, downspout outlets, landscaping and nearby surfaces. Show the customer any visible damage and record in writing whether they approved the repair as a change order.

Keep the prep message, the scope and any change approvals in writing, not just in a phone call. If a customer says three months later that nobody mentioned the cracked splash block, a dated photo and a sent message settle it.

A worked example: a 150-foot seamless replacement

Say a homeowner approves an example price of $2,100 to replace 150 feet of old sectional gutter with 6-inch seamless aluminum, five 3x4 downspouts, splash blocks at each outlet, and haul-away of the old gutters. In this example town, the building department confirmed no permit is needed for that replacement. Three days out, the pro sends this:

Hi Dana, we're set for Thursday, arrival 8:00 to 8:30. Scope: 150 ft of 6-inch seamless aluminum gutter in white, .032 gauge, five 3x4 downspouts with splash blocks, old gutters hauled away. The city building department confirmed no permit is needed.

Not included: fascia, soffit or roof-edge repair, painting and underground drains. If we find rot once the old gutters are off, we'll stop, show you photos and price it before doing anything.

Please move the cars from the side driveway and pull the grill and patio chairs off the back wall by Wednesday night. Keep the dog in during work. We water-test every run before we leave. Storms or high wind would mean a new date, and we'd tell you the day before.

Prices here are examples only. The message takes about ten minutes to write once and a few minutes to adapt for each job after.

How do I know if my pre-job messages are working?

Count the calls and texts asking when you're coming or what the customer needs to do, and divide by jobs. The formula: check-in rate = check-in calls and texts ÷ jobs × 100.

In an example month with 12 installs and 9 check-in calls, the rate is 75%. If the next month has 12 installs and 3 check-in calls after you start sending the prep message, the rate is 25%. Track day-of surprises, like a car still parked under the gutter line, the same way. A notebook tally is enough to see the trend.

Gutter customer messages: when and what
When What it covers
Scope At booking Material, size, downspouts, exclusions
Permit At booking Needed or not, who pulls it, cost
Prep list 2–3 days out Cars, grills, kids, pets, weather
Arrival Morning of Window, running late if needed
Summary Same day after Water test, photos, findings

What pros ask next

Does the customer need to be home during a gutter install?

A customer rarely needs to be home for the whole gutter install, but someone should be reachable by phone. Ask for a quick walk-around at the start to confirm downspout spots and point out visible damage, and another at the end to watch the water test. Gate codes, pets and parked cars should be settled the day before, so the crew never waits on an answer.

What if the customer asks for gutter guards on install day?

Gutter guards added on install day are new work, so write a change order before the crew installs any. Put the guard type, footage and price in a short written message, and get a written reply approving the change. A spoken yes on the driveway is easy to forget by the time the invoice arrives. Guards that need a second trip should get their own date in writing.

How many days before a gutter job should I send the prep message?

Send the gutter prep message two to three days before the job, which gives the customer time to move cars, clear the patio and ask questions. Follow with a short confirmation the evening before or the morning of, repeating the arrival window. A prep message sent only the night before often lands too late for anyone to move a trailer or rearrange a day.

What should I say if the customer wants a downspout moved after work starts?

Moving a downspout after work starts changes where roof water goes, so explain the tradeoff before agreeing. Show where the new outlet would discharge and whether extra elbows, an extension or a splash block are needed. Write the change and any added price in a message, and wait for a written yes. Water aimed toward a foundation or walkway can turn into a complaint later.

References

  1. Gutter sizing by roof flow rate, watertight joints, compatible materials, 1-gallon water test, permit before covered work, New York State Department of State
  2. Example of a city guide to which work needs a building permit, City of New Orleans
  3. OSHA ladder angle, ladder extension and fall protection rules applied to gutter work, Occupational Health & Safety

From Service Penguin

How Service Penguin does this

Service Penguin keeps gutter customers informed from booking to cleanup: arrival windows and a morning arrival time, running-late notices, a post visit summary with photos, and a free customer app with one message thread. Every message is kept word for word on the customer's page. It's free to use. See how it works for gutter pros.

Free to use. No monthly bill.

We get paid when you get paid.

Create your free account

You might also like

Browse all articles →

New answers, by email

Stay up to date

New answers for service pros, by email.

Submitting subscribes you to emails from Service Penguin. You can unsubscribe any time.